Turkmenistan welds 124 km of TAPI pipeline toward Herat

Image
Turkmenistan welds 124 km of TAPI pipeline toward Herat

ASHGABAT -- November 24, 2026 -- Turkmenistan has welded and assembled 124 kilometres of the TAPI gas pipeline between the Turkmen border at Serhetabat and Herat. That is about 82% of the 150.7 kilometres of right-of-way prepared so far, by our calculation. Turkmengaz deputy chair Myrat Archayev said in early October that the section would be finished by the end of 2026, which leaves 38 days.

Officials and satellite images place the pipeline head at different points near Herat

Turkmen officials said at an oil & gas expo in Ashgabat in late October that the pipeline had reached the outskirts of Herat. They put the welded length at approximately 80% of the route and said hydrostatic testing is under way section by section. Satellite images published by RFE/RL on November 7 indicate the pipeline had reached an area about 22 kilometres from Herat's western industrial area.

The gap between prepared right-of-way and welded pipe is 26.7 kilometres (150.7 minus 124). The Turkmen government is financing the project, which reportedly costs about $600 million.

Gas supply terms for Herat remain unnegotiated after an August memorandum

During an August visit to Afghanistan, Turkmenistan's paramount leader Gurbanguly Berdymukhamedov signed a memorandum of understanding. It covers Turkmen natural gas supplies and a gas distribution network for Herat and its vicinity. Volume and pricing remain to be negotiated.

Turkmenistan is also interested in a trans-Afghan power line along the TAPI route. It would allow Turkmen electricity exports to Afghanistan and Pakistan.

Archayev says the Kandahar extension has no funding level or construction targets

Archayev said in early October that continuing TAPI towards Kandahar Province in southern Afghanistan would stay a Turkmen government priority in 2027. He added that a funding level had yet to be finalized and no specific construction targets had been set. TAPI is designed to run from Herat across Afghanistan to Pakistan and India.

Eurasianet reports that Pakistani and Indian interest in Turkmen gas appeared to wane in the early 2020s. It says the disruption to Gulf oil supplies from the US-Iran conflict seems to have revived the project's appeal.

At the Ashgabat expo, Pakistan's envoy to Turkmenistan, Faryal Leghari, reiterated Islamabad's commitment to TAPI. She acknowledged significant political and economic obstacles, including issues behind a low-level conflict between the Taliban and Pakistan that has disrupted cross-border trade. She said Pakistan favours resolving them through consultations, flexibility and cooperation among all stakeholders.