Turkmenistan welds 124 km of TAPI pipeline toward Herat

Image
Turkmenistan welds 124 km of TAPI pipeline toward Herat

ASHGABAT -- November 24, 2026 -- Turkmenistan has welded and assembled 124 kilometres of the TAPI gas pipeline between the Turkmen border at Serhetabat and Herat. That is about 82% of the 150.7 kilometres of right-of-way prepared so far, by our calculation. Turkmengaz deputy chair Myrat Archayev said in early October that the section would be finished by the end of 2026, which leaves 38 days.

Officials and satellite images place the pipeline head at different points near Herat

Turkmen officials said at an oil & gas expo in Ashgabat in late October that the pipeline had reached the outskirts of Herat. They put the welded length at approximately 80% of the route and said hydrostatic testing is under way section by section. Satellite images published by RFE/RL on November 7 indicate the pipeline had reached an area about 22 kilometres from Herat's western industrial area.