Statnett freezes data center grid queue of 34 GW until August 2027

Image
Statnett freezes data center grid queue of 34 GW until August 2027

OSLO -- November 27, 2026 -- Norwegian transmission system operator Statnett has stopped granting new grid reservations to data centers, leaving a request pipeline of about 34 gigawatts (GW) against national peak demand of about 25 GW. The pause began on 9 November and runs until at least August 2027, when a new system is due to take effect.

Requests therefore exceed peak demand by about 36%, by our calculation. Only 0.8 GW of data center capacity is connected today.

Reserved capacity is five times what is connected

The queue breaks down as follows:

  • Connected: 0.8 GW
  • Reserved capacity: 4.2 GW
  • In the queue: 10.8 GW
  • At the inquiry stage: 18 GW

Reserved capacity is about 5.3 times the connected base. Connected and reserved capacity together come to 5.0 GW, equal to about 20% of peak demand. The remaining 28.8 GW is queued or still at inquiry.

Statnett has also stopped approving facility functionality under the Regulation on System Responsibility (fos) § 14 while it sets functional requirements for data centers. These will cover when facilities must stay connected during disturbances, how quickly their load may change and how to limit grid fluctuations. Projects with reserved capacity keep their place but still need approval before connecting. Existing connections are not affected.

Half the queue wants power before the pause ends

About half of the queue has asked for power by the end of 2028, roughly 17 GW by our calculation. With no new reservations until August 2027 at the earliest and grid build-out still to follow, those dates look out of reach for established operators and newcomers alike, according to the report.

Satellite imagery cited in the report shows how much construction is missing. In the UK, almost two-thirds of 2027-28 capacity has no building under way. In the Nordics the share is just over a third. In Norway, about half of the 1.5 GW due in 2027-28 shows new construction, or roughly 0.75 GW, but a single project accounts for most of it.

Grid operators in Great Britain, Germany and Denmark have all tightened connection rules since 2025, moving away from first-come, first-served queues toward projects that can show progress.

Government licensing scheme closes the door on new crypto mining

The government announced the licensing scheme on the same day as the Statnett pause. New crypto sites will not be permitted. Existing ones cannot get more grid capacity and could face restrictions once transitional arrangements expire. The report does not give the expiry date.

Norway has six operating crypto data centers with about 0.2 GW combined. Some operators are already converting to AI. Data center power use in the NO3 price area fell from late 2025 as one large site stopped mining ahead of its conversion, and it is now rising again.

Net exports could fall 71% by 2030

Hydro supplies about 90% of Norway's power, and decades of surplus have kept electricity prices below those in most of Europe. Under normal hydrology, rising demand from data centers and other consumers could cut net exports from 14.3 terawatt-hours (TWh) in 2027 to 4.1 TWh in 2030. That is a drop of 10.2 TWh, or about 71%.

In a dry year, Norway could become a net importer, and winter prices could reach about €290 per megawatt-hour.

The government wants the data center industry to help build gas power with carbon capture and storage and offshore wind. Both have long lead times. Until new supply arrives, the pause gives Statnett more control over incoming demand and helps limit price risk for households and industry.