Statnett

Statnett freezes data center grid queue of 34 GW until August 2027

Image
Statnett freezes data center grid queue of 34 GW until August 2027

OSLO -- November 27, 2026 -- Norwegian transmission system operator Statnett has stopped granting new grid reservations to data centers, leaving a request pipeline of about 34 gigawatts (GW) against national peak demand of about 25 GW. The pause began on 9 November and runs until at least August 2027, when a new system is due to take effect.

Requests therefore exceed peak demand by about 36%, by our calculation. Only 0.8 GW of data center capacity is connected today.

Reserved capacity is five times what is connected

The queue breaks down as follows:

  • Connected: 0.8 GW
  • Reserved capacity: 4.2 GW
  • In the queue: 10.8 GW
  • At the inquiry stage: 18 GW

Reserved capacity is about 5.3 times the connected base. Connected and reserved capacity together come to 5.0 GW, equal to about 20% of peak demand. The remaining 28.8 GW is queued or still at inquiry.