Revolution Wind reaches 704 MW as BNEF cuts US offshore outlook 85%

Image
Revolution Wind reaches 704 MW as BNEF cuts US offshore outlook 85%

UNITED STATES -- November 19, 2026 -- Ørsted's $6.2-billion Revolution Wind offshore wind farm came online in November and became the third utility-scale offshore wind project to reach full commercial operations in the United States, according to an Oilprice.com report. At 704 MW across 65 turbines, it is about 23 times the size of the 30-MW Block Island Wind Farm and about 5.3 times the 132-MW South Fork Wind, by our calculation.

The project sits behind South Fork Wind, which began operating off New York in 2024, and Vineyard Wind near Massachusetts.

Revolution Wind costs about 12% less per megawatt than Block Island

The $6.2-billion price tag works out to roughly $8.8 million per MW of capacity. Block Island, the first major US offshore wind farm, cost $300 million for 30 MW, or $10 million per MW. These are nominal dollar figures, not adjusted for inflation or project scope.

Ørsted Starts 200 MW Blackwater Solar Project in New Mexico

Image
Ørsted Starts 200 MW Blackwater Solar Project in New Mexico

Austin – September 30, 2026 -- Ørsted has begun construction on Blackwater Solar, a 200 MW solar farm in Roosevelt County, New Mexico, marking the Danish energy developer's first project in the state.

Project will supply power equivalent to 56,000 homes under long-term contract

Located between Portales and Clovis, Blackwater Solar is backed by a long-term power purchase agreement designed to meet rising industrial electricity demand within the Southwest Power Pool territory. The facility will generate enough electricity annually to power the equivalent of more than 56,000 homes. Ørsted sourced the project's solar panels from domestic manufacturer First Solar. Commercial operations are expected to begin in late 2027.