Uganda delays first oil to June 2027, exposing $380m budget line
UGANDA -- November 24, 2026 -- Uganda has pushed its first commercial oil production and crude exports back to before the end of June 2027, the Uganda National Oil Company (UNOC) and the Petroleum Authority of Uganda (PAU) said. That is about 21 years after commercial reserves were discovered in 2006.
Finance Minister Henry Musasizi told parliament in June that the Ush 84.39 trillion budget for FY2026/27 assumed petroleum revenue of Ush 1.44 trillion (about $380 million). By our calculation, that is roughly 1.7% of total planned spending. Officials did not say whether the projection will be revised.
The PAU blames international supply chain bottlenecks and disruption linked to the war in Iran. It says the Middle East conflict delayed deliveries of parts for metering, electrical instrumentation and telecommunications systems needed to finish the production and evacuation infrastructure.