VANCOUVER -- November 25, 2026 -- Vizsla Silver Corp. has moved first silver production at its wholly owned Panuco silver-gold project in Mexico back by one year, to the second half of 2028 from the second half of 2027, the company said in a Nov. 19 update. The company says the new schedule reflects its expectations for permitting, site readiness and construction timing.
The company has not changed any other parameter of its November 2025 Feasibility Study. That study projects 17.4 million ounces of silver-equivalent (AgEq) output a year over a 9.4-year mine life, an after-tax NPV (5%) of US$1.8 billion, a 111% IRR and a seven-month payback, at US$35.50 per ounce silver and US$3,100 per ounce gold. By our calculation, 17.4 million ounces valued at the US$35.50 silver price is about US$618 million a year, and the nine-plus-year mine life implies roughly 164 million ounces AgEq in total. Vizsla has made no production decision.
Vizsla has ordered about 85% of Panuco's process plant equipment
M3 Engineering & Technology has completed about 50% of engineering, according to the company. About 85% of the process plant equipment currently contemplated has been ordered. Put differently, roughly half of the engineering and about 15% of the equipment orders remain open.
Three development contracts have been awarded: engineering, procurement and construction management (EPCM), mine design and equipment supply. The company cites press releases dated April 23, 2026 and June 16, 2026. The main mining contract is still to be awarded "in due course", so the largest mine-side package remains open. Vizsla says a construction decision will follow completion of detailed engineering, financing and receipt of all required permits.
Security planning sets the pace for a phased return to site
Vizsla is working with Mexican federal authorities and third-party security advisors on additional security infrastructure and on-site support ahead of a phased return to the site. The company says the timing and scope of any return will depend on its own assessment of security conditions and readiness. The release refers to the "tragic events of January 2026" and to the families of colleagues who were lost. It says Vizsla is supporting the Mexican authorities' investigation. The company did not give a date for the return to site.
The US$5 million foundation commitment equals about 0.3% of the study NPV
Vizsla has committed an initial US$5 million to the Vizsla Foundation, which it has been working to establish since February 2026. The sum works out to about 0.3% of the study's US$1.8 billion after-tax NPV. The company also plans to direct a percentage of future profits to the foundation but gave no figure.
The foundation is meant to complement direct assistance to families affected by the January events. It is to focus on education, health and economic development in communities around Panuco in Sinaloa. Its structure and programs have not been published, and the company says details will follow as discussions with families continue.
CEO Michael Konnert said the company is positioned to move into the next phase of development. Dave D'Antonio, P.Eng., Senior Vice President of Technical Services, reviewed and approved the technical information in the release as the Qualified Person.