Silvercorp Raises El Domo Budget to $298.2M, Delays Start to 2027

Image
Silvercorp Raises El Domo Budget to $298.2M, Delays Start to 2027

Vancouver – – November 04, 2026 -- Silvercorp Metals Inc. (TSX/NYSE American: SVM) raised the construction budget for its El Domo Project in Ecuador to $298.2 million, up $14.6 million from the $283.6 million estimate disclosed on February 4, 2026, and pushed its production target to November 2027 after a four-month delay.

The new figure compares with a $248 million budget in the 2021 Feasibility Study. The company attributes the schedule slip to extended rainfall linked to Super El Nino and says the date remains subject to weather and contractor performance.

Ecuador's diesel subsidy removal adds $8.3 million to remaining construction costs

Diesel rose from under $3 per gallon in December 2024 to $5.64 per gallon in October 2026, an increase of $2.70 per gallon, after Ecuador eliminated diesel subsidies. The fuel adjustment is $3.6 million for Package #1 and $4.7 million for Package #2.

Denison Phoenix ISR Mine 24% Built; 2026 Capex Forecast $278.6M

Image
Denison Phoenix ISR Mine 24% Built; 2026 Capex Forecast $278.6M

TORONTO – November 04, 2026 -- Denison Mines Corp. (TSX: DML; NYSE American: DNN) estimates 2026 expenditures at its Phoenix in-situ recovery (ISR) uranium mine at C$278.6 million, after its first quarter of full-scale construction left the project about 24% complete as of September 30, 2026. The company still targets first production in the second half of 2028.

Phoenix spending reaches C$161.1 million year to date

Year-to-date Phoenix expenditures totaled C$161.1 million, including C$105.0 million on construction and construction indirect costs and C$39.0 million on procurement of equipment and materials. Life-to-date procurement spending stands at about C$56.8 million.

For the fourth quarter of 2026, Denison forecasts C$39.9 million in procurement payments, C$68.5 million in construction and construction indirect costs, and C$9.1 million in engineering, PCM and owner's costs.

SEMI: 300mm Fab Equipment Spending to Hit $227B by 2029

Image
SEMI: 300mm Fab Equipment Spending to Hit $227B by 2029

San Francisco – October 14, 2026 -- Global 300mm front-end fab equipment spending will reach $149 billion in 2026, up 31% year-over-year, and climb to $227 billion by 2029, according to the latest SEMI 300mm Fab Outlook. SEMI projects investment will keep growing at double-digit rates through the forecast period.

SEMI projects 20 new 300mm fabs or lines will start construction worldwide in 2026

Excluding pure R&D fabs, SEMI expects 18 more construction starts in 2027. In the United States, three fabs or lines are projected to begin construction in 2026 and four in 2027.

SEMI also projects 13 new 300mm fabs or lines worldwide will begin operations or ship first silicon in 2026, rising to 23 in 2027.

Telecom Capex Rises 5% in H1 2026, But Long-Term Growth Stays Flat

Image
Telecom Capex Rises 5% in H1 2026, But Long-Term Growth Stays Flat

Redwood City – October 06, 2026 -- Worldwide telecom capital expenditure climbed approximately 5 percent year-over-year in the first half of 2026, outpacing expectations set at the start of the year, according to Dell'Oro Group. The uptick follows several years of declining operator investment.

Equipment revenues track capex gains across six core programs

Aggregate manufacturer revenues across Broadband Access, Microwave & Optical Transport, Mobile Core Network, Radio Access Network, and High End Router & Aggregation also rose roughly 5 percent Y/Y in the first half of 2026, mirroring the capex trend.