ALBANY, N.Y. -- November 24, 2026 -- Soluna Holdings (NASDAQ: SLNH) reported third-quarter revenue of $15.1 million, up 80% from Q3 2025, while gross profit swung to a loss of $1.9 million and net loss widened to $34.3 million. By our calculation, the prior-year quarter's revenue was about $8.4 million. Excluding the gross presentation of pass-through electricity, the company puts growth at 29%.
Gross profit fell from a $2.3 million profit in Q3 2025, a swing of $4.2 million. Soluna attributes the drop mainly to $3.0 million of unscheduled turbine repairs at the Briscoe Wind Farm, which it bought in April 2026. Without the repairs, gross profit would have been $1.1 million, still about 52% below the year-earlier figure. Average hashprice fell 37%, which reduced proprietary mining and profit-share hosting revenue.
Adjusted EBITDA loss widened to $7.5 million from $6.4 million, an increase of about 17%. The company cites the turbine repairs and higher G&A, mainly legal and consulting fees for Kati 2 development and new site evaluation.
Net loss widens 33% on debt extinguishment and stock compensation
Net loss rose by $8.5 million, about 33%, from $25.8 million in Q3 2025. The absence of a $22.0 million fair value adjustment loss from the prior-year quarter was more than offset by other items. Debt extinguishment moved $15.8 million unfavorably: a loss on the Generate prepayment in 2026 against a gain on the NYDIG settlement in 2025. Non-cash stock-based compensation rose $14.0 million, and cash G&A rose $3.1 million.
Soluna cuts debt principal 80% since June after repaying Generate Capital
Soluna prepaid its Generate facilities at Dorothy 1A and Dorothy 2 for $19.1 million in August. On October 22 it repaid the rest of the Generate credit facility, which had helped finance the Briscoe acquisition. Together the payments cleared the $27.5 million of principal outstanding at June 30. The facility is terminated and Generate's liens are released.
Total debt principal fell from $37.9 million at June 30 to $7.7 million, a reduction of $30.2 million, or about 80%. Unrestricted cash stood at $109.3 million on September 30, up 43% from $76.4 million at year-end 2025. That is about 14 times the debt principal remaining after the October repayment. Soluna raised $37.7 million through its ATM program in Q3 and $170.1 million year to date through the ATM and the Yorkville SEPA.
On October 16, stockholders raised authorized common stock from 375 million to 1.0 billion shares, about 2.7 times the old ceiling. They also approved share issuance above Nasdaq's 20% limit under the Yorkville SEPA.
Two Texas AI projects rest on non-binding letters of intent
At Kati 2, the prior prospective tenant's exclusivity period ended, and Soluna remarketed the site. In November it signed a non-binding letter of intent with a new prospective tenant for 118 IT MW at the planned 350+ MW campus, no more than about 34% of planned capacity. The company did not name the tenant or disclose lease terms or financing for either project.
CEO John Belizaire said, "Our focus is converting the AI projects in our pipeline to signed leases."
At Dorothy 3, Soluna acquired 397 acres on August 24 for a planned 300 MW campus. On October 20 it signed a subscription agreement for a joint venture, 51% Applied Digital and 49% Soluna, to build a planned 50 MW Phase 1 facility, about 17% of the planned campus. ChronoScale has signed a non-binding letter of intent to lease that facility. Closing is expected by year-end 2026, subject to remaining conditions. On November 9, the Briscoe County Commissioners Court approved a Chapter 312 tax abatement for Phase 1. Construction began at both sites in October.
At Kati 1, the final 14 MW was completed on September 8, fully energizing the 83 MW site. Revenue from the new K1BC phase was first recognized in Q3, and a mid-September substation outage temporarily affected part of the site. Ryan Carver joined as Chief Development Officer in July to lead AI infrastructure development.
In September, Soluna received ERCOT Base Load classifications for 266 MW of existing interconnection capacity: 166 MW at Kati, including the planned Kati 2 expansion, and 100 MW at Dorothy. The classifications remain pending completion of ERCOT's verification process. A further 50 MW request at Dorothy is under study.