NASA seeks 20-kW lunar reactor, one-fifth of its 2025 target

Image
NASA seeks 20-kW lunar reactor, one-fifth of its 2025 target

WASHINGTON -- November 27, 2026 -- NASA put out to bid on November 23 a 20-kilowatt lunar nuclear reactor, one-fifth of the 100-kilowatt machine the administration promised for 2030 in August 2025. Bids for the Lunar Reactor-1 (LR-1) are due by December 21.

The reactor is to be ready to launch by 2030 and run five years without maintenance. NASA says the output is enough for about 16 American homes. The Energy Department says US suppliers cannot yet provide the fuel it needs, high-assay low-enriched uranium (HALEU).

White House cut the 2030 target in April, pushing 100 kilowatts into the 2030s

In August 2025, then-interim NASA chief Sean Duffy framed the 100-kilowatt goal as a race with China. It was more than double the 40-kilowatt designs NASA had been funding, by our calculation 2.5 times. Katy Huff, the Energy Department's former top nuclear official, said she found "no evidence" the figure had been considered beyond it being bigger. An April White House memo set the 2030 reactor at a minimum of 20 kilowatts and moved the 100-kilowatt version into the 2030s. It gave no reason.

Winning bidders get 18 months to build and test a non-nuclear version

The design must survive more than two weeks of darkness at the lunar south pole, keep running after any single failure and operate with little contact from Earth. Shielding must hold extra radiation to 5 rem a year for astronauts a kilometer away, according to Nuclear Newswire. The real reactor will not run at power until it reaches the Moon.

HALEU supply has no US commercial source before 2029

HALEU is uranium enriched to between 5% and 20%. According to POWER magazine, Russia's Rosatom has been the only commercial seller, and China can also produce it at scale. The Energy Department is drawing fuel for NASA's 2028 Mars spacecraft, SR-1 Freedom, from government stocks, including material held by the nuclear weapons agency. SR-1 is a 20-kilowatt nuclear-electric vehicle that will supply data for LR-1's design.

In January, Washington committed $2.7 billion to domestic enrichment, including $900 million to Centrus Energy, which expects to produce new HALEU in Ohio by 2029. That is one year before the reactor's 2030 launch-readiness date. The Government Accountability Office warned in August that production "is unlikely to scale quickly enough" to meet demand. The Energy Department has not said where LR-1's fuel will come from.

Russia and China target 2033-2035 for their lunar power plant

Roscosmos chief Yury Borisov said in 2024 the two countries plan a lunar power plant around 2033-2035. In December 2025, Roscosmos hired contractor Lavochkin to build one by 2036, with Rosatom involved. Neither country has disclosed its size.

NASA plans to spend $20 billion over seven years on a south pole base and to launch its first element in December.