Kentucky Power seeks approval for 760-MW gas plant to serve TeraWulf

Image
Kentucky Power seeks approval for 760-MW gas plant to serve TeraWulf

ASHLAND, Kentucky – November 13, 2026 -- Kentucky Power asked the Kentucky Public Service Commission (PSC) to approve a 760-MW combined-cycle natural gas plant next to its Big Sandy unit in Louisa and a new substation in the EastPark Industrial Park area. Both would serve TeraWulf's planned Muskie Data Campus in Grayson, which is expected to draw up to 1 gigawatt of contracted demand in phases by 2029. The proposed plant's 760 MW equals about 76% of that 1,000-MW ceiling, by FairsOnline's calculation.

TeraWulf would fund $100 million in winter credits for residential customers

If the PSC approves the agreement, TeraWulf will fund $100 million in winter bill credits for Kentucky Power's residential customers. The credits start in 2029 and run over the first 10 years of the contract, which works out to about $10 million a year. Kentucky Power also expects the project to deliver more than $500 million in fixed-cost rate offsets to customers over the life of the agreement. Together, the two items exceed $600 million.

Kentucky Power serves about 162,000 customers in 20 eastern Kentucky counties. Spread across all of them, $100 million would equal roughly $617 per customer, or about $62 a year. Only residential customers qualify, so the per-recipient amount would be higher.

TeraWulf agrees to pay financing costs for the Big Sandy plant

TeraWulf has agreed to pay the estimated financing costs of building the Big Sandy generation facility, in addition to all applicable service charges. Kentucky Power's large-load tariff separately requires data centers to provide financial backing for the cost of serving them before they connect to the grid. The company says these terms are designed to ensure TeraWulf pays the costs of its new demand. It also says it signed the White House Ratepayer Protection Pledge. The company did not disclose the construction cost of the plant.

Kentucky Power announced the amended agreement with TeraWulf in October. The new filings are the next step in seeking regulatory approval.

PSC decisions on the plant and substation could come by mid-2027

The generation facility and the transmission infrastructure each need a separate Certificate of Public Convenience and Necessity from the PSC. Depending on the commission's review schedule, decisions could come as early as mid-2027. TeraWulf's phased ramp-up to 1 GW by 2029 is subject to regulatory approval and construction schedules, according to the company. The winter credits begin in 2029.