HOUSTON — November 16, 2026 -- A supplier guide published on October 27, 2026 uses the City of Houston's FY2026–2030 wastewater plan, about $3.8 billion in planned improvements, to show how to read a capital improvement plan (CIP) as a sales signal. Spread over five fiscal years, the plan averages roughly $760 million a year by our calculation.
The guide says the program is financed through pay-as-you-go funding and revenue bonds, and names the Water and Sewer System Consolidated Construction Fund as the funding source. It links the work to state and federal requirements and to a consent decree involving the city, the U.S. Environmental Protection Agency and the Texas Commission on Environmental Quality. Priorities include sewer rehabilitation, force mains and lift stations, treatment-plant improvements and facility consolidation. The guide does not say how the $3.8 billion splits between pay-as-you-go funding and bonds.
Units and fiscal-year ranges can distort a project's size and timing
Houston's wastewater tables are reported in $ thousands. A line showing 78,787 equals about $78.8 million, not $78,787, a thousandfold difference.
Plan horizons also differ. Houston's covers five fiscal years. Alexandria, Virginia, publishes a 10-year program covering FY2027 through FY2036, twice the span. The guide adds that a project showing spending in FY2028 does not necessarily start work in January 2028, because fiscal-year start dates vary by agency.
Wausau's fire station plan shifted within four months
In June 2026, Wausau, Wisconsin, proposed $700,000 for architectural design in 2027 and $28 million for construction of a new fire station in 2028. The construction line was 40 times the design request, which made up about 2.5% of the combined $28.7 million.
By October, the city's proposed 2027 budget had deferred the $700,000 design request while officials considered other options for the facility. The guide says a future construction year is a planning marker, not an RFP date.
The guide ranks funding status above headline project value
The guide says an adopted plan is not the same as a funded one, because adopted multi-year plans can still hold projects that depend on future budgets, grants or bonds. It tells suppliers to log the plan's status (proposed or adopted), each project's funding source and its funding status: secured, appropriated, proposed, pending or unfunded.
By its own example, a $50 million project that still needs funding may deserve less immediate attention than a $2 million design package that is funded and authorized. The larger project is 25 times the size of the smaller one.
The guide also recommends comparing each new CIP with the previous version. Suppliers should look for new, advanced, slipped, dropped and re-funded projects, and for changes in phase or cost.
It lists seven public signals to track as next steps, from budget hearings and council or board agendas to feasibility studies, grant awards or bond authorizations, design milestones, procurement notices and contract awards.