ExxonMobil approves US$12.5bn Longtail gas project in Guyana

Image
ExxonMobil approves US$12.5bn Longtail gas project in Guyana

SPRING, Texas -- November 19, 2026 -- ExxonMobil has taken a final investment decision on Longtail, a gas and condensate development offshore Guyana, committing an additional US$12.5 billion with start-up expected in 2030. The floating production storage and offloading (FPSO) vessel is designed to produce up to 250,000 barrels of condensate per day. By our calculation, that equals about 28% of the roughly 900,000 barrels per day of oil the Stabroek block produces now, though the two products are not directly interchangeable.

Longtail becomes the eighth Stabroek project and targets non-associated gas

Longtail is the eighth development in the southeastern portion of the Stabroek block. ExxonMobil says it targets non-associated gas and condensate-rich reservoirs. The FPSO is designed to process 1.2 billion standard cubic feet of gas per day. The project is expected to include about 45 subsea production and injection wells.

Dividing US$12.5 billion by 45 wells works out to about US$278 million per well. This is a rough ratio only, because the release does not break down the spend.

Gas exports are not yet committed. ExxonMobil says gas from Longtail could be transported to shore by pipeline, subject to future investment decisions, market demand and the development of necessary infrastructure. The company did not say whether the US$12.5 billion is the gross project cost or ExxonMobil's share.

Stabroek is set to double from four producing projects to eight by 2030

ExxonMobil produces about 900,000 bpd from four Stabroek projects. It expects the fifth, Uaru, to start up in the fourth quarter, which it says would lift production above 1 million bpd.

Construction is progressing on Whiptail and Hammerhead, the sixth and seventh approved projects. ExxonMobil expects Whiptail to begin production in 2027 and Hammerhead in 2029. Longtail follows in 2030, one year after Hammerhead and about four years after the investment decision.

ExxonMobil Guyana operates Longtail and holds 45% of the Stabroek block

ExxonMobil Guyana Limited, an ExxonMobil affiliate, is the Longtail operator and holds a 45% interest in the Stabroek block. Hess Guyana Exploration Ltd. holds 30% and CNOOC Petroleum Guyana Limited holds 25%. The two partners together hold 55%.

About 6,000 Guyanese support Stabroek block operations, according to ExxonMobil. Since 2015, ExxonMobil Guyana and its contractors have spent more than US$3.9 billion with Guyanese suppliers. The planned Longtail investment of US$12.5 billion is about 3.2 times that cumulative local spend, by our calculation.