AUSTIN -- November 24, 2026 -- DPR Construction has completed Hotel Trinity, a 14-story, 258-room Autograph Collection hotel at 311 E. 5th St. in downtown Austin, after a 24-month build that ran from October 2024 to September 2026. Roughly 1,200 craft workers logged more than 175,000 hours, which works out to about one worker hour per square foot of the 177,000-square-foot building.
White Lodging developed the hotel, and it is now open. The release gives no opening date and no project cost.
Labor input works out to about 680 hours per guest room
By our calculation, the 175,000 hours equal roughly 680 hours for each of the 258 guest rooms. The building averages about 686 square feet of gross area per room (177,000 divided by 258). The release also lists 20 luxury suites but does not say whether they are counted within the 258 rooms.
More than 50 trade partners worked on the site. Headcount peaked at about 325, or roughly 27% of the 1,200 total who worked on the project. Spread across all 1,200 workers, the hours average about 146 per person.
Meeting and event space totals about 6,700 square feet, or about 3.8% of the building. The hotel also houses the Yacht Club, a ground-floor seafood restaurant, and Sundeck Social, a rooftop pool and social club.
DPR spent a year on utilities before a two-week demolition
Site preparation required demolishing two existing structures in a compressed two-week schedule. DPR says it first ran a year-long effort to relocate, disconnect and refeed active utilities serving neighboring properties. That work included telecom and internet services and a new water feed for the adjacent Antone's Nightclub.
The two buildings shared a wall with Antone's. DPR says it wrote a sequenced demolition plan to separate the structures without disrupting the venue. The team also monitored noise and vibration and ran dust and erosion control, street cleaning and coordinated hauling.
The utility work for neighbors therefore took about 26 times as long as the demolition itself (roughly 52 weeks against two).
Prefabricated wall panels went up during overnight shifts
The exterior wall panels were manufactured off-site and installed overnight. DPR says the method sped up the building enclosure, reduced effects on downtown traffic and nearby businesses, and reached an expedited dry-in milestone that limited weather delays. The release gives no dry-in date and no schedule saving.
Bryan Kent, DPR's Central Texas business unit leader, said early coordination among owner, designers, trade partners and builder helped the team manage cost pressures and keep the project moving. Jeff Hanson, White Lodging's executive vice president of design and construction, said the aim was a destination blending luxury, privacy and personality.
The design and engineering team included architect PFVS, civil engineer HR Green, MEP engineer Blum Consulting Engineers, interior designer FlickMars Hospitality and demolition partner JR Ramon Demolition.