NEWNAN, Georgia -- November 28, 2026 -- Coweta County voters will decide on Jan. 12 whether to repeal the rezoning for Project Sail, a $17 billion data center campus on about 829 acres southwest of Atlanta. Commissioners approved the rezoning 3-2 on April 7. Probate Judge Carrie B. Markham ordered the election.
The ballot question goes beyond one project. It would also delete data centers from the county zoning code and ban data centers and cryptocurrency mining operations in all zoning districts.
Petition cleared the legal threshold by 94 signatures
Opponents filed the petition Oct. 16 under the Home Rule provision of the Georgia Constitution. It required 10,971 signatures, 10% of 109,703 active electors, according to Markham's Nov. 23 order. Organizers submitted 14,820, and the county's elections director verified 11,065. That is about 75% of those submitted, and 94 above the requirement.
Atlas Development, the Buford-based company that filed the rezoning, objected on Oct. 23. Markham dismissed the objection, finding that under Georgia Supreme Court precedent no party has standing to object to a Home Rule petition, and that Atlas's objection was not verified. The state's high court opened the route last year in a case over Hogg Hummock on Sapelo Island, ruling unanimously that a McIntosh County zoning ordinance was subject to the same referendum procedure.
The county will pay for the vote and run it on its normal equipment and precincts. The court will certify the result.
Project's projected tax revenue has fallen from $1 billion to about $100 million a year
Atlas first projected more than $1 billion a year in local taxes. The Atlanta Journal-Constitution found that figure erroneous. Prologis, the San Francisco-based industrial REIT under contract to take over the project, now projects about $100 million a year. State filings list $163 million.
Atlas's filings with the Georgia Department of Community Affairs describe 13 buildings of about 378,000 square feet each, about 4.9 million square feet in total by our calculation, completed by the end of 2036. Build-out value is $17,161,900,000. Water demand is 9.1 million gallons a day, with 3.03 million gallons a day of sewage and 800 tons of solid waste a year. Prologis has pitched a smaller version of nine buildings and about 4.3 million square feet, drawing roughly 900 megawatts.
The rezoning moved the land near Sargent and Wagers Mill roads from Rural Conservation to Industrial. Commissioners Alphonso Smith, Jeff Fisher and John Reidelbach voted in favor. Residents sued in May in Coweta County Superior Court, alleging commissioners ignored the land's conservation designation and its role in groundwater recharge. That case is pending.
Prologis says the petition does not change its commitment
Prologis said in October that the petition "does not change our commitment to Project Sail." The company did not say how it would respond to a repeal. Coweta communications manager Cathy Wickey said the county is still assessing implications and anticipates legal questions and challenges.
If the measure passes, no data center or crypto mine could be zoned anywhere in the county. Vivian Allen of Citizens for Rural Coweta said the group expects turnout on Jan. 12.