Katanning airport shuts for 33 days in AUD 1.56m runway rebuild

Image
Katanning airport shuts for 33 days in AUD 1.56m runway rebuild

KATANNING -- November 24, 2026 -- The Shire of Katanning began a scheduled closure of Katanning Aerodrome on 16 November for runway reconstruction and resealing priced at about AUD 1.56 million, excluding GST. Reopening is planned for around 18 December 2026. By our calculation the closure spans about 33 calendar days, of which seven had elapsed by 22 November.

The closure falls mainly on emergency aviation. The Shire plans daytime medical evacuations by helicopter for the Royal Flying Doctor Service, and night-time transfers via Wagin or Kojonup. Firefighting aircraft can operate from Wagin, Kojonup or Gnowangerup. The Shire's announcement does not establish a loss of scheduled commercial passenger services.

At 33 days, the Katanning closure is 10 days, or about 23%, shorter than the 43-day closure of Canada's Natashquan Airport earlier in 2026.