Deutsche Energy Terminal

Stade LNG terminal Energos Force opens after 35-month delay

STADE -- November 24, 2026 -- German Economy Minister Katherina Reiche has opened the floating LNG terminal Energos Force in Stade, roughly 35 months after the December 2023 start date originally planned, by our calculation. According to the environmental group Deutsche Umwelthilfe (DUH), the delay of almost three years stemmed from a dispute between the project companies Deutsche Energy Terminal (DET) and Hanseatic Energy Hub (HEH).

DUH responded with a demand for an immediate LNG moratorium. The group says a halt would stop the build-up of further overcapacity and fossil dependence.

DUH federal managing director Sascha Müller-Kraenner argues that rising gas prices and unreliable partner countries make LNG expansion questionable. He contrasted Reiche's attendance in Stade with the climate conference under way in Antalya. DUH wants the energy system built on renewables and electrification instead.