Adura starts Jackdaw gas flow three weeks after UK approval
UNITED KINGDOM -- November 24, 2026 -- Adura started Jackdaw gas flow from its UK North Sea platform on Monday, about three weeks after the British government approved the project at the end of October. By our calculation, the gap between approval and first gas is roughly 23 days.
Adura is the company into which Shell and Equinor merged their UK North Sea oil and gas assets. It says Jackdaw will produce enough gas at peak to heat the equivalent of around 1.4 million UK homes.
Jackdaw gas runs through existing Shearwater infrastructure
The gas will pass through the Shearwater production hub and on to the St Fergus gas terminal in Aberdeenshire, Scotland, Adura said. From there it will be supplied to homes and businesses across Britain.