TOOELE -- November 25, 2026 -- The U.S. Army signed a nonbinding term sheet on November 3 giving REalloys (Nasdaq: ALOY) exclusive negotiations on about 200 acres at Tooele Army Depot in Utah for heavy rare earth processing, with a potential 75-year lease and a right of first offer on production. The structure differs from earlier federal rare earth support: MP Materials received more than $1 billion in combined financing and USA Rare Earth a $1.6 billion package, together more than $2.6 billion by our calculation.
REalloys would finance and build the facility. The Army would supply land and a security perimeter. REalloys would pay fair-market rent, and the Army would collect participation rent once commercial operations start. As described, the deal involves no government equity, no taxpayer-funded construction and no grants. Jeff Waksman, the Army's principal deputy assistant secretary for installations, energy and environment, said the arrangement expands the critical minerals base "without putting taxpayer dollars at risk."
The Army would be first in line to buy output, but the term sheet is not a purchase order and the Army's own procurement process still applies.
Federal money has gone to mines and separation, not to metallization
The Center for Strategic and International Studies identifies rare earth metallization as the least developed and hardest capability to rebuild outside China. That step turns separated oxides into high-purity metals and alloys. By the account behind the Tooele deal, North America's capacity to make defense-grade metals and magnets from heavy rare earths has barely changed despite the funding. The same account puts China's share of global rare earth processing at approximately 90% and says it supplies nearly all dysprosium and terbium used in U.S. weapons magnets.
REalloys targets about 36 tonnes a year of heavy rare earth oxide from Saskatchewan
REalloys holds an exclusive 80% offtake from the Saskatchewan Research Council (SRC) processing facility. The SRC plant targets annual capacity of about 525 tonnes of NdPr metal, 30 tonnes of dysprosium oxide and 15 tonnes of terbium oxide. If the 80% share applies to those targets, REalloys would take about 420 tonnes of NdPr and 36 tonnes of dysprosium and terbium oxide combined. Initial NdPr metallization is targeted for commissioning in Q1 2027. REalloys expects high-purity materials from SRC as early as Q4 2026.
In September the company appointed Dr. Muhammad Imran, SRC's former CTO with 17 years of rare earth processing experience, as Chief Operating Officer. Its Euclid, Ohio facility has worked with the Department of Defense, Department of Energy and NASA. In March it won a Defense Logistics Agency contract to develop modular metallization technology for samarium and gadolinium. Feedstock agreements span Saskatchewan, Wyoming, Appalachia, Kazakhstan, Brazil and Greenland, including a 15-year offtake for 15% of Phase 1 production from Critical Metals' Tanbreez project.
Because REalloys carries the capital cost, its balance sheet matters. It closed an approximately $100 million institutional private placement in June 2026 and reports $122.4 million in cash with virtually no debt. Neither party has disclosed the rent terms, the facility's cost or its planned capacity.
Pentagon restrictions on Chinese rare earths take effect January 1, 2027
Expanded Pentagon procurement rules restricting Chinese-origin rare earth materials in U.S. weapons systems start 38 days after this report's date. Beijing suspended its export controls on seven heavy rare earth elements only until January 10, 2027, nine days after the Pentagon rules start.
Evolution Metals & Technologies (Nasdaq: EMAT) is working toward the same date from the magnet side. President Andrew Knaggs says a Pentagon rule is expected to extend a mine-to-magnet restriction on neodymium-iron-boron magnets across the full supply chain from January 1, 2027. The company is expanding its Pohang, South Korea, plant toward annual capacity above 10,000 metric tons. In October it raised fiscal 2026 revenue guidance to $10 million to $11 million and kept a fiscal 2027 target of $400 million to $460 million, a jump of roughly 36 to 46 times by our calculation. The company says that outlook is not based on contracted volumes, and its release lists its ability to continue as a going concern among the risks.
Perpetua's Army tungsten award commits $18 million of up to $40 million
Perpetua Resources (Nasdaq: PPTA) has a different Army arrangement: a cost-share, not a land lease. On October 26 it said the Army's Defense Ordnance Technology Consortium had awarded it up to $40 million over 36 months to explore for tungsten at its Stibnite project in Idaho, matched by Perpetua. Only the first phase, about $18 million or 45% of the ceiling, is committed. In its November 13 third-quarter update Perpetua reported $443.4 million in unrestricted cash. Its $2.9 billion EXIM loan, approved in May, is not expected to close until the first quarter of 2027.