SAN FRANCISCO -- November 24, 2026 -- Armada was named a priority team leader in the U.S. Department of Commerce's American SI Exports Program on Nov. 16, heading a consortium with Microsoft and Dell that offers super intelligence (SI) infrastructure to foreign buyers. The announcement also disclosed a letter of intent with Australian SI factory and colocation provider WinDC for 3 GW of capacity by the end of 2030, about 270 times the 11 MW planned for the first phase, by our calculation.
Commerce designation brings prioritized export licensing and federal financing referrals
Designated consortia receive U.S. Government advocacy for strategic projects, prioritized processing of export license applications at the Bureau of Industry and Security, and priority access to federal financing referrals. U.S. Government representatives can also help broker deals between trusted foreign buyers and designated consortia. Armada's package sits on a "menu" that U.S. and Foreign Commercial Service representatives will offer to foreign buyers worldwide.
The consortium is called the American Sovereign SI Stack. It combines Armada's Galleon and Leviathan modular data centers and the Armada Platform with Dell compute and storage and Microsoft Azure Local and Foundry Local. Armada says customers own the hardware, data, models and keys, and can run them in-region, private or air-gapped.
CEO Dan Wright said a country can go "from signature to sovereign SI in months, not years." That timeline is the company's claim; the release gives no delivery data to test it.
WinDC letter of intent scales from 11 MW to 3 GW across Australia and New Zealand by 2030
The two companies plan about 11 MW on Armada Leviathans across five Australian states, using curtailed wind and solar power to produce tokens. A further 230 MW is targeted for 2027, about 21 times the first phase and about 241 MW in total. The 2030 target is 3 GW across about 40 sites in Australia and New Zealand, which works out to an average of 75 MW per site. Armada describes a single Leviathan as a 10 MW unit.
The companies estimate more than $30 billion in project investment. More than $20 billion of that is Armada's U.S.-manufactured infrastructure, roughly two-thirds of the minimum total. Spread across 3 GW, the $30 billion equals at least $10 million per MW, and the Armada hardware alone at least about $6.7 million per MW. The companies did not disclose who will finance the project.
The WinDC plan is a letter of intent, and the release names no definitive agreement. It is the only foreign deal named in the announcement, and its hardware falls under the export-licensing priority the designation provides.
Armada builds its units in Gilbert, Arizona, and Dublin, Ireland
Armada manufactures its American-designed modular data centers at Galleon Forge One in Gilbert, Arizona, and, for Europe, at Galleon Forge Two in Dublin. The company works with Johnson Controls on manufacturing and says the Arizona plant supports U.S. jobs and supply chain.