Salazar Resources Reports US$66.2M Spent at Fully Funded El Domo Mine
Image
Vancouver – September 13, 2026 -- Salazar Resources Limited (OTCQB: SRLZF) (TSXV: SRL) (FSE: CCG) has spent US$66.2 million on construction of the Curipamba-El Domo polymetallic project in Ecuador through June 30, 2026, with commissioning targeted for July 2027 under a fully funded build.
Salazar holds a 25% carried interest while Silvercorp funds and operates the build
Salazar retains a 25% carried interest in Curipamba-El Domo, located in Ecuador's Bolivar and Los Rios provinces. Silvercorp holds the remaining 75%, operates the project and is funding construction, meaning Salazar pays nothing to reach production but does not control the schedule or budget.